Climbing Wall Play Unit Removal, Reinstallation, and Surfacing in South East England

Our team was commissioned to remove a number of existing climbing wall play units from one site in South East England and reinstall them at a separate location.

Scroll

The Brief

The equipment was in good condition, and the client wished to retain and reuse it rather than replace it, providing a cost-effective and sustainable solution.

The objective of the project was to safely break out the existing units, transport them to the new site, reinstall them in full working order, and provide compliant safety surfacing to ensure the area met current standards.

Swipe for more

Key features

The project focused on the careful relocation and reinstatement of specialist play equipment, combined with the installation of new safety surfacing. Key aspects of the works included

Removal of existing climbing wall units: The climbing wall units were carefully broken out and dismantled, with attention paid to preserving the integrity of the equipment during removal

Reinstallation at a new site: The units were transported and reinstalled at the new location, positioned to suit the layout and ensure appropriate safety clearances and fall zones

New safety surfacing: New safety surfacing was installed beneath and around the climbing wall units to provide impact protection and ensure full compliance with current play safety requirements

Foundations and fixings: New foundations and fixings were installed where required to ensure the climbing walls were secure, stable, and suitable for long-term use

Cost-effective and sustainable solution: By reusing existing equipment and combining it with new surfacing, the project delivered a high-quality, sustainable solution while reducing waste and overall costs

Obstacles and Solutions

The project presented several technical and logistical challenges

Careful breakout and handling: Breaking out the existing units required precision and care to prevent damage, allowing the equipment to be successfully reused

Coordination between sites: The removal, transport, and reinstallation phases were carefully scheduled to ensure an efficient workflow between both locations

Safety and compliance: All works, including the installation of new safety surfacing, were completed in line with relevant safety standards, with final checks carried out to confirm the area was safe for use

Want to find out about how we work?

Get in touch

Conclusion

The completed project successfully relocated and reinstated the climbing wall play units, providing them with a new lease of life at their new site. The addition of new safety surfacing ensured the area met current standards and provided a safe environment for users.

The client was extremely pleased with the outcome, particularly the cost savings achieved through reusing existing equipment and the seamless integration of new surfacing. The project highlights our ability to deliver efficient, sustainable, and safety-focused play area solutions.